General

  • Belgrade Waterfront Shopping mall, Serbia
  • Investor: Eagle Hills
  • Partner: Arhi Pro d.o.o. Belgrade

Highlights

  • Building area: cca 300.000 sqm
  • 3 transformer substations
  • 17 transformers, 32 MVA installed power
  • 5 DG sets: 4.1 MVA
  • Simultaneous power: 18.5 MW
  • More than 2.5 km of busbar trunking systems

Our work

Detailed design (DD) of:

  • Transformer substations
  • Main MV and LV power supply – busbar trunking systems, cables and cable trays